Location within country: Rwanda (Kacyiru, Gasabo ) |
Eng. BUNANE Jean Luc, Certified Engineer, Head of Mission & Team coordinator
Daniel MANIRIHO, Technical staff, supervisor Eng. MBARAGA Roger, Technical staff
|
|
Name of the procuring entity: ZIGAMA CSS |
No of key staff: 3 Persons |
|
Address: PO Box:4772 Kigali [email protected], www.zigamacss.rw KG178 St 3, Gasabo-Remera |
Duration of assignment: 2 weeks |
|
Start date (month/year): From: March 2023 |
Completion date(month/year): March 2023 |
|
Name of associated consultants: N/A |
|
|
Name of senior staff (project Director/coordinator, team leader) involved and functions performed: Eng. BUNANE Jean Luc, Managing Director / Technical Team Coordinator) |
||
Narrative description of the project: Supply & Installation of soundproof walls and openings |
||
Description of actual services provided by your staff: Coordination of work on site, execution and supervision. |